Basic Understanding of Customized CNC Hydraulic Fixture Cycles
2025-07-09

June and July are usually the peak shipping season for CNC hydraulic fixtures. At this point, let's take a look at the production process and production cycle of customized CNC hydraulic fixtures from Ovanst. After finalizing the customer's design, the following is the production process and cycle time of CNC hydraulic fixtures.


When it comes to customized CNC hydraulic fixture lead time, we usually discuss it into several categories of situations such as small and large CNC hydraulic fixtures, standardized or non-standard used, domestic or imported parts, and other situations.


Basic Understanding of Customized CNC Hydraulic Fixture Cycles


First, CNC hydraulic fixture raw materials and electronic parts procurement. Steel, aluminum and other raw materials procurement generally takes 1-3 days, hydraulic components such as cylinders cylinders, etc. There is a difference between domestic and imported, domestic cylinder procurement cycle is usually 25-30 days, non-standard imported cylinders is about 60 days.


Second, CNC hydraulic fixture processing and manufacturing. Structural parts, small fixtures, for clamping specific, support head, support seat, positioning pins, cylinder seat and guide system, etc. for turning, milling, drilling, CNC and other series of processing. The machined parts are then heat treated to improve metal hardness and wear resistance. This is followed by surface treatment. After heat treatment and surface treatment, the metal needs to be finished and QC inspected again to meet the preset requirements. This process generally takes 15-20 days for small fixtures such as electronic control box bodies, and 30-35 days for thick base plates, for example.


Third, CNC hydraulic fixture installation. Small fixtures can generally be installed in about 1 day, while large or structurally complex fixtures can take anywhere from 3-7 days.


Fourth, testing. It takes 1 day to test the hydraulic fixture after production. CMM testing takes 1 day. In summary, the production of a set of high-precision CNC hydraulic fixtures, need to be based on its size and complexity, etc. to make a comprehensive judgment, for small fixtures, the delivery time generally falls on the 42 ~ 52 days, while for large fixtures or complexity of the fixture when the higher degree of fixtures, the delivery time is required to 95 ~ 105 days.


What kind of CNC hydraulic fixture you need, welcome to discuss with us.